July 16, 2020

I-440 Re-design

I-440 Re-design

In November 2018, Stansell Electric partnered with Kiewit, TDOT, NES, and Metro Public Works, to start the I-440 re-design project. Fast forward 18 months, and substantial completion was achieved! With a committed team of field leaders, crafts people, and project managers; the team installed:

395 light poles with LED fixtures
2 traffic intersections
8 miles of fiber
22 Radar Detection Systems
6 LED DMS Signs
11 CCTV Units

Date July 16, 2020